May 28 Renovation Updates

OUTSIDE:

Utility work for water and sewer will begin this week on the west side of Gorgas.  A fence will be put into place to enclose an area between the crosswalk near the Round House and the west end of the porch at Capstone.  A protected alternate walkway and accessible entry point into the building will be provided. 

INSIDE:

  • Removal of old steam pipes from the tunnel (underneath 102 and 104A) is complete. Sanitary and water lines will be installed in this tunnel.
  • Abatement around the elevator on the mezzanine level is complete.
  • Abatement in 203 is complete.
  • Demolition of JavaCity has begun.
  • Installation of temporary partitions has begun on 4M and upper floors.
  • Abatement is scheduled for Monday in 303.
  • Installation of new sanitary line will begin today.
  • Site work for connection to water meter underneath Capstone Drive will begin today.
  • Staff elevator cab has been disassembled.
  • Demolition in 203 and 104A has begun.
  • A wall will be constructed in 202.
  • The partition for work in 205 and 205C will be built this week.