Renovation Update December 10

Work to build the construction barrier for the restroom project on 4th floor will begin on Friday, December 13.  On December 20, after 5:00 p.m., work will begin on 4th floor to remove the carpet in the elevator lobby, the area south of the elevator lobby, and conference rooms 401 and 402. The library will be officially closed after 5:00 p.m. on December 20.   New carpet will be installed on fourth floor in the area south of the elevator lobby where the cubicles are currently installed, in Steven Turner’s office suite, in 402 and 401.  New ceiling tiles will be installed in the space south of the elevator lobby.  At the completion of the restroom work, new floor tiles and a new ceiling will be installed in the elevator lobby.  The conference room, 402, will get a facelift, which will include carpet, new ceiling and enhanced entry, along with some technology upgrades. 

Pending inspection and final approval, the restrooms on Floors 2 and 2M are scheduled to be completed and available for use by the beginning of the spring semester.   The elevator lobby on Floor 2, as well as the large space near the Circulation Desk is also scheduled to be completed by the beginning of spring semester.

Currently, the staff elevator project is scheduled to be completed by the end of March, 2020.

Leave a Reply

Your email address will not be published. Required fields are marked *