UAF:
The construction project at the University Archive Facility is
moving along and is close to being on schedule. We still anticipate that
the building will be completed in late fall of 2019. A reconfiguration of
the existing janitor’s closet and restroom in the Annex are part of the
construction plan because the changes were required by code. This part of
the project has been inside the current building and has created a lot of
commotion, but should be completed by the end of August. There will be a
scheduled water outage at the Annex tomorrow so that the contractor can make a
new connection to the old sprinkler system in the building. A new pump
that will regulate the pressure in the existing fire suppression system will be
installed. Orders for the compact moveable shelving and the Raymon lift
are being finalized. The Raymon lift will be used to pick items from the
compact moveable shelve in the UAF. The shelving in the Special
Collections area of the UAF will be 24 feet tall. In the General
Collections area, there are plans to install shelving that will be various
heights, with the tallest sections measuring 18 feet tall.
JavaCity:
The JavaCity construction project is nearing completion. The
ceilings, walls, and floors have been replaced and the whole area looks fresh
and bright. New plumbing and drains have been installed, as well as new
countertops. Electrical and data lines have been installed to accommodate
new points of sale kiosks as well as other functions in the space. The
moveable security gate is in place and the millwork for the JavaCity service
counter and work space is scheduled to be installed on August 8. JavaCity
is expected to be fully operational when classes begin on August 21.
Second Floor Meeting Room Project:
A lot of progress has been made in the renovation of 205C and 205
to create a multi-use space for meetings and events. Sheetrock is going
up, as well as celling grids. Wall partitions and door openings have been
framed for the new storage area and catering area, as well as the new entrance
into the north side of the room. This week, the track for the moveable
wall will be installed. Backing for the video wall has been installed in
each of the two areas and electrical and data lines have been routed around the
room. This project is on track to be completed in November, 2019.
Restrooms and Adjacent Areas Project:
Work on the first floor restroom has gained momentum and should be
complete by the middle of September. The second floor restroom is also
moving along according to schedule and should be turned back over to us in
October/early November. The Circulation Desk on second floor has been
removed, and the tile and ceilings in that area and to the right and left of
the Circulation Desk have been removed. New ceiling grid, ceiling tiles
and lights are being installed in those areas. Behind the Circulation
Desk, the storage area for equipment will be revamped to provide more efficient
storage space for cameras, laptops, and other equipment circulated from
the Circulation Desk. The second floor elevator lobby will be refreshed
with a new coat of paint, new floors and a new ceiling. A new water fountain,
equipped with water bottle filler, will be installed in that foyer.
All water fountains that are currently located in elevator lobbies will be
replaced with new water fountains that are equipped with water bottle
fillers. Access to all materials and all study rooms remains open.
The Circulation Desk is operating from a temporary location on the second floor
of Gorgas Library in Pearce Foyer.
The schedule for the restrooms has been revised and the completion
date for the restrooms will be June/July 2020. I will get a revised
schedule to you very soon so that you will know when the work will be done on
the floor where you work. The contractor anticipates being able to pick
up the pace as they move through the building, but the demolition work is very
tedious and slow due to the extremely sturdy construction techniques that were
used when the existing spaces were built. The first floor restroom
presented many unexpected issues that were not shown in the drawings from the
original construction of that area (i.e., depth of slab that had to be
cut was 10” instead of 4”). As we move upward through the building, we
will have a plan for how your space will be affected and will share that with
you.
Elevator Project:
The installation of the new staff elevator is moving forward at
what seems to be a snail’s pace. Demolition in the old shaft is
complete. This week, you will be aware of the work that will be going on
in the basement. The foundation for the new elevator machine room will be
constructed over the next week or so. In order to do that, the existing
foundation in that area will have to be saw-cut and the debris will be carried
out. Then the space will be back-filled and a new foundation will be
poured. This will create the base for the elevator machinery. The
completion date for the staff elevator is estimated to be in late
January/February, 2020. Once the staff elevator is operational, one of
the passenger elevators will be taken off-line and the replacement of that car
and controls will begin. Then, when that passenger elevator is operational,
the other passenger elevator will be taken off-line for the same type of
work. The shaft for the passenger elevators will not have to be altered,
which should allow this project to move forward more quickly than the staff
elevator, and without so much dust and noise. This project is scheduled
to be completed by the end of July 2020.